Two-Week Construction Schedule

Planned construction activities for this week and next week in Downtown Fresno. View the schedule as a list, a weekly calendar, or highlighted on the project site plan.

This Week

Oct 19 – Oct 25

Mon, Oct 19

Working NowNight Work

F Street · Inyo St to Kern St

Install 16" DI water main — night work — Crew 1

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Mon, Oct 19

Working NowNight Work

Fulton Street · Merced St to Tuolumne St

Construct manhole; install 12" sewer main — night work — Crew 3

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Mon, Oct 19

Working NowNight Work

H Street · H St & Tulare St intersection

Install 24" DI water main at the intersection — night work — Crew 4

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Mon, Oct 19

Working NowDay Work

Fulton Street · Stanislaus St to Tuolumne St

Install 16" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Tue, Oct 20

Working NowNight Work

F Street · Inyo St to Kern St

Install 16" DI water main — night work — Crew 1

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Tue, Oct 20

Working NowNight Work

Fulton Street · Merced St to Tuolumne St

Construct manhole; install 12" sewer main — night work — Crew 3

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Tue, Oct 20

Working NowNight Work

H Street · H St & Tulare St intersection

Install 24" DI water main at the intersection — night work — Crew 4

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Tue, Oct 20

Working NowDay Work

Fulton Street · Stanislaus St to Tuolumne St

Install 16" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Wed, Oct 21

Working NowNight Work

F Street · Inyo St to Kern St

Install 16" DI water main — night work — Crew 1

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Wed, Oct 21

Working NowNight Work

Fulton Street · Merced St to Tuolumne St

Construct manhole; install 12" sewer main — night work — Crew 3

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Wed, Oct 21

Working NowNight Work

H Street · H St & Tulare St intersection

Install 24" DI water main at the intersection — night work — Crew 4

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Wed, Oct 21

Working NowDay Work

Fulton Street · Stanislaus St to Tuolumne St

Install 16" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Thu, Oct 22

Working NowNight Work

F Street · Inyo St to Kern St

Install 16" DI water main — night work — Crew 1

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Thu, Oct 22

Working NowNight Work

Fulton Street · Merced St to Tuolumne St

Construct manhole; install 12" sewer main — night work — Crew 3

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Thu, Oct 22

Working NowNight Work

H Street · H St & Tulare St intersection

Install 24" DI water main at the intersection — night work — Crew 4

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Thu, Oct 22

Working NowDay Work

Fulton Street · Stanislaus St to Tuolumne St

Install 16" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Fri, Oct 23

Working NowDay Work

Fulton Street · Stanislaus St to Tuolumne St

Install 16" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Sun, Oct 25

Working NowNight Work

F Street · F St & Kern St

Remove existing asbestos-cement sewer pipe; install new sewer and backfill manhole — night work — Crew 1

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Sun, Oct 25

Working NowNight Work

Fulton Street · Merced St to Tuolumne St

Construct manhole; install 12" sewer main — night work — Crew 3

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Next Week

Oct 26 – Nov 1

Mon, Oct 26

Working NowNight Work

F Street · F St & Kern St

Remove existing asbestos-cement sewer pipe; install new sewer and backfill manhole — night work — Crew 1

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Mon, Oct 26

Working NowNight Work

Fulton Street · Merced St to Tuolumne St

Construct manhole; install 12" sewer main — night work — Crew 3

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Mon, Oct 26

Working NowDay Work

H Street · Mariposa St to Tulare St

Install 24" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Mon, Oct 26

Working NowDay Work

H Street · H St & Merced St intersection

Install 24" DI water main at the intersection — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Tue, Oct 27

Working NowNight Work

F Street · F St & Kern St

Remove existing asbestos-cement sewer pipe; install new sewer and backfill manhole — night work — Crew 1

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Tue, Oct 27

Working NowNight Work

Fulton Street · Merced St to Tuolumne St

Construct manhole; install 12" sewer main — night work — Crew 3

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Tue, Oct 27

Working NowDay Work

H Street · Mariposa St to Tulare St

Install 24" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Tue, Oct 27

Working NowDay Work

H Street · H St & Merced St intersection

Install 24" DI water main at the intersection — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Wed, Oct 28

Working NowNight Work

F Street · F St & Kern St

Remove existing asbestos-cement sewer pipe; install new sewer and backfill manhole — night work — Crew 1

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Wed, Oct 28

Working NowNight Work

Fulton Street · Merced St to Tuolumne St

Construct manhole; install 12" sewer main — night work — Crew 3

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Wed, Oct 28

Working NowDay Work

H Street · Mariposa St to Tulare St

Install 24" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Wed, Oct 28

Working NowDay Work

H Street · H St & Merced St intersection

Install 24" DI water main at the intersection — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Thu, Oct 29

Working NowNight Work

F Street · F St & Kern St

Remove existing asbestos-cement sewer pipe; install new sewer and backfill manhole — night work — Crew 1

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Thu, Oct 29

Working NowNight Work

Fulton Street · Merced St to Tuolumne St

Construct manhole; install 12" sewer main — night work — Crew 3

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning by 6 AM

Thu, Oct 29

Working NowDay Work

H Street · Mariposa St to Tulare St

Install 24" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Thu, Oct 29

Working NowDay Work

H Street · H St & Merced St intersection

Install 24" DI water main at the intersection — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Fri, Oct 30

Working NowDay Work

H Street · Mariposa St to Tulare St

Install 24" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Fri, Oct 30

Working NowDay Work

H Street · H St & Merced St intersection

Install 24" DI water main at the intersection — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Construction schedules are subject to change due to weather, underground utility conflicts, field conditions, material availability, City direction, and other unforeseen conditions.