Tue, Sep 8
F Street · Kern St to Tulare St
Backfill new sewer main to the Tulare St manhole — night work — Crew 1
- Hours:
- 9:00 PM – 6:00 AM
- Traffic:
- Night lane closures with flaggers
- Parking:
- No overnight parking
- Access:
- Restored each morning by 6 AM
IIGC Downtown Water & Sewer Improvements · Construction Updates Provided by Katch Environmental
Planned construction activities for this week and next week in Downtown Fresno. View the schedule as a list, a weekly calendar, or highlighted on the project site plan.
Tue, Sep 8
Backfill new sewer main to the Tulare St manhole — night work — Crew 1
Tue, Sep 8
Install 24" DI water main — Crew 2
Tue, Sep 8
Install 16" DI water main (final segment) — Crew 3
Tue, Sep 8
Install 16" DI water main — Crew 3
Wed, Sep 9
Backfill new sewer main to the Tulare St manhole — night work — Crew 1
Wed, Sep 9
Install 24" DI water main — Crew 2
Wed, Sep 9
Install 16" DI water main (final segment) — Crew 3
Wed, Sep 9
Install 16" DI water main — Crew 3
Thu, Sep 10
Install 16" DI water main through intersection — night work — Crew 1
Thu, Sep 10
Install 24" DI water main — Crew 2
Thu, Sep 10
Install 16" DI water main (final segment) — Crew 3
Thu, Sep 10
Install 16" DI water main — Crew 3
Fri, Sep 11
Install 24" DI water main — Crew 2
Fri, Sep 11
Install 16" DI water main (final segment) — Crew 3
Fri, Sep 11
Install 16" DI water main — Crew 3
Mon, Sep 14
Install 16" DI water main — Crew 1
Mon, Sep 14
Install 24" DI water main — Crew 2
Mon, Sep 14
Install 16" DI water main — Crew 3
Tue, Sep 15
Install 16" DI water main — Crew 1
Tue, Sep 15
Install 24" DI water main — Crew 2
Tue, Sep 15
Install 16" DI water main — Crew 3
Wed, Sep 16
Install 16" DI water main — Crew 1
Wed, Sep 16
Install 24" DI water main — Crew 2
Wed, Sep 16
Install 16" DI water main — Crew 3
Thu, Sep 17
Install 16" DI water main — Crew 1
Thu, Sep 17
Install 24" DI water main — Crew 2
Thu, Sep 17
Install 16" DI water main — Crew 3
Fri, Sep 18
Install 16" DI water main — Crew 1
Fri, Sep 18
Install 24" DI water main — Crew 2
Fri, Sep 18
Install 16" DI water main — Crew 3
Construction schedules are subject to change due to weather, underground utility conflicts, field conditions, material availability, City direction, and other unforeseen conditions.