IIGC Downtown Water & Sewer ImprovementsConstruction Updates Provided by Katch Environmental

Two-Week Construction Schedule

Planned construction activities for this week and next week in Downtown Fresno. View the schedule as a list, a weekly calendar, or highlighted on the project site plan.

This Week

Jul 20 – Jul 26

Mon, Jul 20

Working NowDay Work

F Street · Mono St to Kern St

Install 12" sewer main (Mono toward Kern); new 48" manhole at F & Inyo — Crew 1

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Mon, Jul 20

Working NowNight Work

G Street · Inyo St to Kern St

Install 12" PVC water main — night work — Crew 2

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning

Mon, Jul 20

Working NowDay Work

Tulare Street · H St to Federal Alley

Install 24" DI water main — Crew 3

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Mon, Jul 20

Working NowDay Work

Calaveras Street · H St to Broadway St

Pothole existing utilities along new water main alignment — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Rolling lane closures
Parking:
Posted no-parking
Access:
Maintained

Tue, Jul 21

Working NowDay Work

F Street · Mono St to Kern St

Install 12" sewer main (Mono toward Kern); new 48" manhole at F & Inyo — Crew 1

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Tue, Jul 21

Working NowNight Work

G Street · Inyo St to Kern St

Install 12" PVC water main — night work — Crew 2

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning

Tue, Jul 21

Working NowDay Work

Tulare Street · H St to Federal Alley

Install 24" DI water main — Crew 3

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Tue, Jul 21

Working NowDay Work

Calaveras Street · H St to Broadway St

Pothole existing utilities along new water main alignment — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Rolling lane closures
Parking:
Posted no-parking
Access:
Maintained

Wed, Jul 22

Working NowDay Work

F Street · Mono St to Kern St

Install 12" sewer main (Mono toward Kern); new 48" manhole at F & Inyo — Crew 1

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Wed, Jul 22

Working NowNight Work

G Street · Inyo St to Kern St

Install 12" PVC water main — night work — Crew 2

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning

Wed, Jul 22

Working NowDay Work

Tulare Street · H St to Federal Alley

Install 24" DI water main — Crew 3

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Wed, Jul 22

Working NowDay Work

Calaveras Street · H St to Broadway St

Pothole existing utilities along new water main alignment — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Rolling lane closures
Parking:
Posted no-parking
Access:
Maintained

Thu, Jul 23

Working NowDay Work

F Street · Mono St to Kern St

Install 12" sewer main (Mono toward Kern); new 48" manhole at F & Inyo — Crew 1

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Thu, Jul 23

Working NowNight Work

G Street · Inyo St to Kern St

Install 12" PVC water main — night work — Crew 2

Hours:
9:00 PM – 6:00 AM
Traffic:
Night lane closures with flaggers
Parking:
No overnight parking
Access:
Restored each morning

Thu, Jul 23

Working NowDay Work

Tulare Street · H St to Federal Alley

Install 24" DI water main — Crew 3

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Thu, Jul 23

Working NowDay Work

Calaveras Street · H St to Broadway St

Pothole existing utilities along new water main alignment — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Rolling lane closures
Parking:
Posted no-parking
Access:
Maintained

Fri, Jul 24

Working NowDay Work

F Street · Mono St to Kern St

Install 12" sewer main (Mono toward Kern); new 48" manhole at F & Inyo — Crew 1

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Fri, Jul 24

Working NowDay Work

Tulare Street · H St to Federal Alley

Install 24" DI water main — Crew 3

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Fri, Jul 24

Working NowDay Work

Calaveras Street · H St to Broadway St

Pothole existing utilities along new water main alignment — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Rolling lane closures
Parking:
Posted no-parking
Access:
Maintained

Next Week

Jul 27 – Aug 2

Mon, Jul 27

Working NowDay Work

F Street · Kern St to Tulare St

Install 12" sewer main (Kern to Tulare); new 48" manhole at F & Kern — Crew 1

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Mon, Jul 27

Starting SoonDay Work

F Street · Ventura St (Cesar Chavez) to Mono St

Install 16" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
Posted no-parking
Access:
Maintained

Mon, Jul 27

Working NowDay Work

Tulare Street · H St to Federal Alley

Install 24" DI water main (continued) — Crew 3

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Mon, Jul 27

Working NowDay Work

Calaveras Street · H St to Broadway St

Install 16" DI water main — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Rolling lane closures
Parking:
Posted no-parking
Access:
Maintained

Tue, Jul 28

Working NowDay Work

F Street · Kern St to Tulare St

Install 12" sewer main (Kern to Tulare); new 48" manhole at F & Kern — Crew 1

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Tue, Jul 28

Starting SoonDay Work

F Street · Ventura St (Cesar Chavez) to Mono St

Install 16" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
Posted no-parking
Access:
Maintained

Tue, Jul 28

Working NowDay Work

Tulare Street · H St to Federal Alley

Install 24" DI water main (continued) — Crew 3

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Tue, Jul 28

Working NowDay Work

Calaveras Street · H St to Broadway St

Install 16" DI water main — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Rolling lane closures
Parking:
Posted no-parking
Access:
Maintained

Wed, Jul 29

Working NowDay Work

F Street · Kern St to Tulare St

Install 12" sewer main (Kern to Tulare); new 48" manhole at F & Kern — Crew 1

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Wed, Jul 29

Starting SoonDay Work

F Street · Ventura St (Cesar Chavez) to Mono St

Install 16" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
Posted no-parking
Access:
Maintained

Wed, Jul 29

Working NowDay Work

Tulare Street · H St to Federal Alley

Install 24" DI water main (continued) — Crew 3

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Wed, Jul 29

Working NowDay Work

Calaveras Street · H St to Broadway St

Install 16" DI water main — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Rolling lane closures
Parking:
Posted no-parking
Access:
Maintained

Thu, Jul 30

Working NowDay Work

F Street · Kern St to Tulare St

Install 12" sewer main (Kern to Tulare); new 48" manhole at F & Kern — Crew 1

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Thu, Jul 30

Starting SoonDay Work

F Street · Ventura St (Cesar Chavez) to Mono St

Install 16" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
Posted no-parking
Access:
Maintained

Thu, Jul 30

Working NowDay Work

Tulare Street · H St to Federal Alley

Install 24" DI water main (continued) — Crew 3

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Thu, Jul 30

Working NowDay Work

Calaveras Street · H St to Broadway St

Install 16" DI water main — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Rolling lane closures
Parking:
Posted no-parking
Access:
Maintained

Fri, Jul 31

Working NowDay Work

F Street · Kern St to Tulare St

Install 12" sewer main (Kern to Tulare); new 48" manhole at F & Kern — Crew 1

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Fri, Jul 31

Starting SoonDay Work

F Street · Ventura St (Cesar Chavez) to Mono St

Install 16" DI water main — Crew 2

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
Posted no-parking
Access:
Maintained

Fri, Jul 31

Working NowDay Work

Tulare Street · H St to Federal Alley

Install 24" DI water main (continued) — Crew 3

Hours:
9:00 AM – 4:00 PM
Traffic:
Lane closures with flaggers
Parking:
No parking in work zone
Access:
Maintained

Fri, Jul 31

Working NowDay Work

Calaveras Street · H St to Broadway St

Install 16" DI water main — Crew 4

Hours:
9:00 AM – 4:00 PM
Traffic:
Rolling lane closures
Parking:
Posted no-parking
Access:
Maintained

Construction schedules are subject to change due to weather, underground utility conflicts, field conditions, material availability, City direction, and other unforeseen conditions.