Week of Oct 19 – Oct 25, 2026
Work Completed Last Week
All crews remobilized after the RFI responses: night crews advanced the F Street 16-inch main at the F & Inyo intersection, built the new sewer manhole at Merced & Fulton, and saw cut and installed 24-inch main on H Street. Day crews progressed the Fulton Street water main from Calaveras to Stanislaus and completed bypass tie-in preparation at H & Inyo.
Work Happening This Week
NIGHT WORK (Sunday–Thursday nights, 9:00 PM – 6:00 AM): • F Street — 16-inch water main from Inyo Street to Kern Street (Crew 1). • Fulton Street — sewer manhole and 12-inch main, Merced to Tuolumne (Crew 3). • H Street — 24-inch main at the H & Tulare intersection (Crew 4). DAY WORK (Monday–Friday, 9:00 AM – 4:00 PM): • Fulton Street — 16-inch water main, Stanislaus to Tuolumne (Crew 2).
Work Planned Next Week
NIGHT WORK (Sunday–Thursday nights, October 25–29, 9:00 PM – 6:00 AM): • F Street at Kern Street — removal of the existing asbestos-cement sewer pipe under the required handling and safety procedures, and installation of new sewer pipe with manhole backfill (Crew 1). • Fulton Street — sewer manhole and 12-inch main continue (Crew 3). DAY WORK (Monday–Friday, October 26–30, 9:00 AM – 4:00 PM): • H Street — 24-inch main from Mariposa Street to Tulare Street (Crew 2) and at the H & Merced intersection (Crew 4).
Important Notices
H Street remains CLOSED to through traffic between Mariposa and Fresno Streets — please follow the posted detour; local and business access is maintained. Night work runs Sunday–Thursday nights at three locations this week (F Street, Fulton Street, and H & Tulare), 9:00 PM – 6:00 AM. Metered parking bags on Tulare, H, Fulton, and Stanislaus Streets are current, and all traffic control plans are approved.
Schedule Changes
The Tulare Street water main (Fulton to Van Ness) has been pushed back again and is on hold — new dates will be posted once confirmed. The bypass installation at H & Inyo is also postponed. H Street work is at the H & Tulare intersection on nights this week, then switches to day shift next week for the Mariposa-to-Tulare segment and the H & Merced intersection. After finishing the F Street water main at Kern this week, the night crew moves to sewer work at F & Kern. The F Street segment from Fresno to Mariposa remains pending City approval.