Week of Sep 7 – Sep 13, 2026
Work Completed Last Week
Night crews finished installing the 12-inch sewer main on F Street from Kern Street to Tulare Street and advanced the Tulare Street water main north of Fulton. Day crews progressed the Calaveras Street final segment and the Fulton Street water main from Calaveras toward Stanislaus.
Work Happening This Week
NO WORK MONDAY, SEPTEMBER 7 (Labor Day). NIGHT WORK (9:00 PM – 6:00 AM): • F Street — backfilling the new sewer main from Kern to Tulare, Tuesday and Wednesday nights (Sep 8–9). • Mono Street & F Street intersection — 16-inch water main installation, Thursday night (Sep 10). DAY WORK (Tuesday–Friday, 9:00 AM – 4:00 PM): • H Street — 24-inch water main from Mariposa Street to Merced Street. • Calaveras Street — final water main segment, Congo Alley to Fulton Street. • Fulton Street — 16-inch water main from Calaveras Street to Stanislaus Street.
Work Planned Next Week
Day work, Monday–Friday (Sep 14–18), 9:00 AM – 4:00 PM: • F Street — 16-inch water main from Mono Street to Inyo Street. • H Street — 24-inch water main continues, Mariposa Street to Merced Street. • Fulton Street — 16-inch water main from Stanislaus Street to Tuolumne Street.
Important Notices
NO WORK on Labor Day, Monday, September 7. Night work runs Tuesday–Thursday nights this week on F Street (9:00 PM – 6:00 AM). Metered parking on Fulton Street will be bagged (no parking) September 10–25 within the work area. All traffic control permits and public notifications are current.
Schedule Changes
Two scopes of work have been pushed back to a later date: the Tulare Street water main north of Fulton (Fulton to Van Ness) and the Fulton Street sewer work between Merced and Tuolumne, including the Fulton & Tuolumne intersection. New dates will be posted once confirmed. The F Street 16-inch water main is back on the schedule — the Mono & F intersection Thursday night, then Mono to Inyo starting September 14.